Load shedding & batteries · Faisalabad, Lahore, Punjab

How does a Solis hybrid handle load-shedding?

Short answer

A Solis S6-EH1P hybrid switches its backup port to battery and solar in under 10 ms (Solis states this for the S6-EH1P-L), so lights, fans and routers on that circuit keep running.

If backup loads are too high, or a motor's start-up surge is too big, it shows Over-Load; Solis says to remove some backup load or move inductive loads off backup.

We plan which circuits go on backup.

Backup planning

Our Faisalabad and Lahore engineers plan Solis backup circuits around what homes need most.