Solar Contract Checklist: What Your Agreement Should Say

Short answer

A good solar contract turns the quotation into binding commitments: who does what, exactly which equipment, how much is paid and when, what "finished" means, which documents you receive at handover, which warranties apply and who handles the net billing paperwork. If something matters to you and it is not written in the agreement or its attached BOQ, assume it is not promised. This checklist covers the clauses to look for before you sign or pay an advance.

This is general guidance for homeowners and businesses in Punjab, not legal advice. For large commercial or industrial contracts, have a lawyer review the agreement.

Quotation, BOQ and contract: how they fit together

For a home system, the "contract" may be a signed quotation with written terms attached. For a factory, it is usually a fuller agreement. Either way, the BOQ should be attached and referred to, so the equipment list cannot quietly change.

Diagram

What a solar contract should say

Scope

Every item by brand and model

Payment

Advance and milestones

Warranty

Manufacturer's and our own

Quotes are valid for 3 days; a 50% advance locks the price.

The 12-point solar contract checklist

#ClauseWhat it should say
1Parties and siteFull names, contact details, site address and electricity connection reference
2Scope of workDesign, supply, structure, installation, testing, commissioning, training; listed clearly
3Customer responsibilitiesRoof access, secure storage, power and water on site, civil work, approvals you must obtain
4Equipment scheduleThe BOQ attached, with exact brand, model and quantity for each main item
5SubstitutionsOnly with your written consent, equal or better specification, and any price difference stated
6Price basisWhat the price includes (transport, taxes, installation), how long it is valid, and whether it is fixed after the advance
7Payment milestonesEach payment tied to an event: advance, delivery, installation, commissioning
8TimelineExpected schedule and the conditions it depends on
9Delivery, ownership and riskWhen equipment becomes yours, who is responsible for it on site, serial numbers recorded at delivery
10Testing, commissioning and acceptanceThe tests done, a commissioning record, and how you sign off
11Handover documents and warrantiesThe document pack, manufacturer warranties in writing, the installer's own warranties and the claim process
12Net billing, changes, cancellation and disputesWho handles DISCO paperwork, how changes are priced, what happens to the advance if either side cancels, how disagreements are settled

The sections below explain the clauses that cause the most trouble.

Scope, exclusions and your responsibilities

Most disputes start with "I thought that was included". The scope should list what the company does, and the exclusions should list what it does not. Common exclusions are roof repairs, civil work, long extra cable runs, DISCO charges and transport to distant sites. Our guide to what a lower solar quote usually leaves out shows the items most often moved to "later".

Your own responsibilities should be written too: giving access to the roof and inverter location, a safe place to store equipment, and any permissions from your housing society or landlord.

Exact models, and the substitution clause

The agreement should name the exact panel, inverter and battery models, not "Tier 1 panels" or "10 kW hybrid inverter". Because stock in Pakistan moves quickly, a model can become unavailable between signing and delivery. A fair substitution clause says:

At delivery, check labels and serial numbers against the BOQ. Our guide on how to check genuine solar panels explains how to verify serials.

Price, validity and taxes

Solar prices follow the dollar rate, import costs, taxes and stock, so most quotations are valid for only a short time. The contract should say:

Our guide to why solar prices change explains the drivers. Quotes are valid for 3 days, and the price is locked once the 50% advance is received.

Payment milestones

Solar projects in Pakistan generally run on advance payment, because equipment must be bought before installation. What protects you is that each later payment is tied to a clear event. A typical structure looks like this, though the stages and amounts vary by project:

  1. Advance on signing, to procure equipment.
  2. A further payment on delivery of equipment to site.
  3. A payment on completion of installation.
  4. The balance on testing and commissioning.

Get a written receipt for every payment. Be cautious of a demand for full payment before any delivery with no written schedule.

Timeline: realistic and conditional

A contract should give an expected schedule, not a promise that ignores reality. Delivery and installation depend on timely payments, equipment availability and site readiness. The agreement should say what happens if either side causes a delay, for example if the roof is not ready or a payment is late. Be wary of a fixed completion date with no conditions at all.

Testing, commissioning and acceptance

"Finished" should mean tested and commissioned, not just panels on the roof. The contract should list the tests or refer to a commissioning checklist, and give you a written record of the results. Our guide on how we test and commission a solar system shows what those checks cover. Agree how small snags are listed and fixed after handover, so the final payment is not stuck over minor items.

Handover documents

Ask the contract to list the document pack you receive. A complete handover usually includes:

Keep these together. Our first 30 days with a new solar system guide explains what to check after handover.

Warranties and service

Two kinds of warranty belong in the agreement:

The contract should also say how to register a complaint and what response to expect. Our solar warranty guide explains product and performance warranties, and our guide to solar system insurance covers storm, theft and fire risks that warranties usually exclude.

Net billing responsibilities

If you plan to export to the grid, write down who does what:

Under the current rules, systems of 25 kW or below need DISCO approval, while larger systems pay a NEPRA fee of Rs 1,000 per kW. Approval is the DISCO's decision, so no installer can honestly guarantee it or its timing. Our net metering and net billing guide covers eligibility and limits.

Solar Works Pakistan prepares and submits the net billing application and documents to your DISCO as part of the project.

Changes, cancellation and disputes

Red flags in a solar agreement

How Solar Works Pakistan sets out its agreements

Our process starts with a site survey, which is normally free, and in-house engineering design. The quotation and BOQ name the brand, model, quantity, specification and warranty of each main item once equipment is selected. Projects generally run on an advance-payment basis, with milestones set to suit the project's size, procurement and installation stages. Small projects can normally be completed in about a week, subject to payment, stock and site readiness; larger projects follow a project-specific schedule.

We complete the tests needed for safe commissioning before handover, then train you on the system, inverter and monitoring app and hand over the project documentation. Manufacturer warranties are. Our own warranties are a 3-year structure warranty and a 1-year service warranty under the applicable project terms, and we target sending service personnel within 48 hours of a registered complaint. After the first year, service is chargeable, and a maintenance contract is available if you want one. See how after-sales service works, what happens during a site survey, our solar installation services and, for factories, industrial and commercial solar.

Get today's price or a free site survey

Send us your bills and any quotation or draft agreement you want to compare.

We serve all of Punjab. You can also contact us online.

Frequently asked questions

Do I need a written contract for a home solar system?

Yes. Even for a home system, a signed quotation with written terms and the BOQ attached protects both sides. Verbal promises about equipment, timelines or warranties are hard to enforce later.

What should a solar installation agreement include?

Scope and exclusions, the exact equipment list, price basis and validity, payment milestones, a conditional timeline, testing and acceptance, the handover document pack, warranties, net billing responsibilities, and rules for changes and cancellation.

How should solar payments be split?

Usually an advance on signing to procure equipment, then payments tied to delivery, installation and commissioning. The exact split varies by project; what matters is that each payment is linked to a clear event and receipted.

Can the installer change the panel model after I sign?

Only if the contract allows it. A fair clause requires your written consent, equal or better specification and a stated price difference.

Should a solar contract guarantee savings?

No. Savings depend on weather, dust, shading, your usage and the tariff. An honest agreement may include an estimate with its assumptions, but not a guarantee.

Who is responsible for net billing approval?

Approval is the DISCO's decision. The contract should say who prepares and submits the documents, who pays the fees and what happens if approval is delayed.

Is this checklist legal advice?

No. It is a practical guide to what a solar agreement usually covers. For large or complex contracts, ask a lawyer to review the terms.

Sources

  1. Net billing approval threshold and NEPRA fee are carried over from our net metering and net billing guide, which lists its own sources, including the NEPRA (Prosumer) Regulations, 2026, SRO 251(I)/2026: https://ke.com.pk/wp-content/uploads/2026/04/8.-NEPRA-Prosumer-Regulations-SRO-251I2026-09-02-26.pdf